WEEK
TWELVE
Monday,
3rd February
And its February
already.
The transporter trailer
has had its new roof fitted at the body builders, so I took Kenny
Kenworth out for a run first thing Monday to blow the cobwebs back out
of her exhaust stack to pick it up. This season will be drier in the box
then.
Back at the workshop
its all action with large and long sections of heavy metal being
cut to lengths to fabricate the under chassis frame. The idea of this
frame is to stiffen up the chassis and to generally lower the centre of
gravity as we intend to mount the engine and gearbox within the cradle
frame, making the truck handle like a go kart.
Photos of this frame
for you to see is a problem as our design is all new and Pav wants to
keep it quiet for a while, although if you visit a truck race meeting
this year you will be able to see it first hand.
This took all week
to fabricate and fit - with the engine being hoisted in to align and manufacture
the engine mountings. By the end of the week my drivers seat and steering
column was in the cab but not necessarily in the right position or order
as shown in photo.

Later in the week
I make contact via email to my friendly engine supplier across the other
side of Europe in the Czech republic. On what's what on their race team
for this season for the 1st time this year.
End of week 12. -
8 weeks to go.
My race engineers
are telling me my truck will be finished end of March. Ill go on
praying because I think they are having a laugh !!
|